Training Standard/5356 Plan, Build, Maintain, and Disassemble Systems
More actions
Official standard. This page transcribes or closely follows an official Skilled Trades Ontario, Electrical Safety Authority, or IATSE document. It is provided for reference and convenience only — it is not the authoritative record. Always confirm current requirements against the original source or Skilled Trades Ontario.
Skill Set 5356.0 from the Training Standard. This skill set carries the largest share of the Certificate of Qualification exam — see Exam Prep.
General Performance Objective
Plan, build, maintain, and disassemble systems by performing visual inspection of system equipment; planning power distribution systems; assembling main and sub-distribution equipment; hanging/mounting system devices; connecting/circuiting system devices; installing practicals and set wiring; diagnosing and troubleshooting practicals, luminaires, and distribution devices; maintaining practicals, luminaires, and distribution devices; and disassembling main and sub-distribution systems and components, according to regulatory requirements, codes, job requirements, manufacturers' recommendations and specifications, site conditions, company policies and procedures, and safety requirements.
Skills
- 5356.01 Perform visual inspection of system equipment
- Including generator sets, transformers, cables, connectors, luminaires and other lighting devices, mounting and hanging equipment, overcurrent protection devices, lenses, screens, safety cables, strain reliefs, and grounding and bonding equipment, by checking for approval markings, capacity, and worn, damaged, missing, corroded, loose, and defective components.
- 5356.02 Plan power distribution systems
- Including physical layout, ventilation, equipment required, capacity of the distribution system, distribution points, physical cable size, panels, boxes, generator sets with frequency control, transformers, dimmers, surge protection, uninterruptible power supplies, optical isolation, grounding and bonding equipment, and isolated power, by checking available capacity, power quality, phasing, and voltage.
- 5356.03 Assemble main and sub-distribution equipment
- Including cables, cable mats, generator sets, transformers, overcurrent protection devices, panels, boxes, grounding and bonding equipment, and physical support systems, by checking connections and routing of cables; visually inspecting, testing and analysing performance and function.
- 5356.04 Hang/mount system devices
- Including luminaires and other lighting devices and effects equipment, by checking for approval markings, capacity, clearances, stability, orientation of equipment, securement and secondary safety attachments, and routing and supporting of cables.
- 5356.05 Connect/circuit system devices
- Including luminaires and other lighting devices and effects equipment, by checking for approval markings, capacity, clearances, stability, orientation of equipment, securement and secondary safety attachments; connecting to selected circuits and testing performance and function.
- 5356.06 Install practicals and set wiring
- Including standard or custom luminaires, cue-light systems and work lights, set practicals, chasers, fixed and dynamic signs, rope lights, light panels and boxes, LEDs, neons, device and equipment boxes, ballasts, relays, control equipment and enclosures, receptacles, and wall switches, by situating, cutting, drilling, and mounting wiring, and connecting wiring to selected circuits.
- 5356.07 Diagnose and troubleshoot practicals, luminaires, and distribution devices
- By checking for approval markings, capacity, clearances, stability, colour temperature, light levels, orientation of equipment, and mountings and connections; inspecting, testing and analysing performance and function.
- 5356.08 Maintain practicals, luminaires, and distribution devices
- Checking clearances, stability, colour temperature, light levels, orientation of equipment, and mountings and connections; exchanging, reconditioning, aligning, storing, or removing devices and components from service.
- 5356.09 Disassemble main and sub-distribution systems and components
- Including lighting, video, audio, and effects equipment; wiring; cables; cable mats; generator sets; transformers; splitters; overcurrent protection devices; isolation devices; distribution boxes and panels; dimmers; and physical support systems, by ensuring all power is disconnected, inspecting, disconnecting, and separating equipment, tagging defective equipment, and preparing equipment for storage/shipment/travel.
- Source: Apprenticeship Training Standard, Skill Set 5356.0, pp.34–39